Scheduled Maintenance: ATS-C / UPS-C – March 28 (07:00–17:00)

Scheduled Scheduled on 03/28/2026 05:00:00 Estimated finish 03/28/2026 15:00:00
As part of our ongoing infrastructure expansion, we will perform scheduled maintenance on ATS-C and UPS-C to support the installation of an additional distribution panel for power feed C.

The maintenance window is scheduled for:

Saturday, March 28, from 07:00 to 17:00

Impact
- No service interruption is expected.
- During this window, both ATS-C and UPS-C will be unavailable.
- All loads normally supplied via DIST-C1 will be transferred to ATS-D via external bypass.
- Power will remain continuously available throughout the maintenance.
- Systems will operate without UPS protection for the duration of the window.
- Generator-backed protection will remain available via ATS-D.

Affected Scope

All infrastructure connected to DIST-C1.

Additional Notes

This maintenance is required to expand capacity and improve long-term resilience of the power infrastructure. Increased activity from electricians and contractors is expected during the window. Certain shared areas, including the loading bay, may be temporarily restricted.

If you have any planned shipments or require access during this time, please coordinate with our operations team in advance.
Related servers / services:
ATS-C / UPS-C / DIST-C1